How to Read and Write Real Estate Legal Descriptions
How to Read and Write Real Estate Legal Descriptions
A plain-English field guide to the systems, words, math and rules behind property descriptions, written so a person can learn from it and an AI can use it as a reference to decode a deed, check it, and map it out. Includes a free deed plotter at the bottom of the page.
1. What a legal description is
A legal description is a set of words that identifies one piece of land (or space) so precisely that it cannot describe any other. It is called “legal” because it has to hold up in a deed, a title policy, a lawsuit or a court order. A street address is not a legal description: addresses change, get reassigned, and say nothing about where the lines are.
A good description is locatable: a competent surveyor who has never seen the property can take the words, go to the ground, and put the corners back where they belong. Every rule in this guide serves that one goal.
The parts of a description
| Part | What it does | Example wording |
|---|---|---|
| Caption (the “frame”) | Names the larger parcel the land sits inside. It limits everything that follows: anything the body describes outside the caption does not pass. | “That portion of Lot 9 of Willow Creek Estates, as per map recorded in Book 41, Page 17 of Maps…” |
| Body (the “focus”) | Traces the exact outline: a point of beginning and a series of calls, or a short-form statement. | “…described as follows: Beginning at…” |
| Exceptions | Takes something out of what was just described. The excepted land stays with the seller (or was never his). | “EXCEPT the westerly 15 feet thereof.” |
| Reservations | Keeps back a new right for the seller in the land being conveyed, such as an easement or minerals. | “RESERVING unto the grantor an easement for ingress and egress over the southerly 20 feet.” |
| Appurtenances | Adds rights that travel with the land. | “TOGETHER WITH a non-exclusive easement for road purposes over…” |
2. How U.S. land got described: a short history
Why one county reads “Lot 4, Block 12” and the next reads “beginning at a stake by a white oak” comes down to who controlled the land first.
| Era / region | System | What you will see in old deeds |
|---|---|---|
| Original colonies and states carved from them (New England, Mid-Atlantic, the Carolinas, Georgia, Virginia, Kentucky, Tennessee, West Virginia, parts of Ohio, Maine, Vermont) | Metes and bounds, laid out by private surveys with no master grid | Trees, stones, stakes, creeks and neighbors as corners; poles, perches and rods for distance; magnetic compass bearings |
| Spanish and Mexican grants (California, New Mexico, Arizona, Florida, Louisiana, Texas) | Large grants (“ranchos,” “sitios”) described by natural features, later confirmed and surveyed by the U.S. | Varas for distance; landmarks such as hills, springs and arroyos; later U.S. patent surveys of the grant boundary |
| Texas | Its own system: the state kept its public land when it joined the Union. Land is identified by survey name, abstract number, block and section from railroad and school land grants | “Survey No. 14, Abstract 822, Block 3, H&TC RR Co. Survey”; leagues, labors and varas |
| Public domain states (most of the country west of the original colonies) | The rectangular Public Land Survey System (PLSS), begun by the Land Ordinance of 1785 | Township, range, section and aliquot parts such as “NE¼ SW¼ Section 22, T4N, R2W” |
| Cities and subdivisions everywhere | Recorded plats (maps) that divide a larger tract into lots and blocks | “Lot 6, Block 2, Riverbend Addition, Plat Book 7, Page 33” |
| Modern era | State Plane Coordinate Systems (created in the 1930s), the NAD 27 and NAD 83 datums, GPS/GNSS | Corners tied to state plane coordinates; a stated basis of bearings and datum |
A few states also offered land registration (the Torrens system), where a court decrees the title and boundary and issues a certificate. It survives in parts of Minnesota, Hawaii, Massachusetts and a few other places. Everywhere else, title runs through recorded deeds in the county recorder’s office.
Public vs. private land and how it moves
- Public land passes from the government to the first private owner by a patent (federal or state). The patent and the original government survey plat are the root of title.
- Private land passes by deed, will, court order or foreclosure. Each transfer should repeat or refer to a description that traces back to the patent or a recorded plat.
- The paper trail lives in the recorder / register of deeds (deeds, plats, easements), the assessor (tax parcel maps, which are useful but not authoritative), the county surveyor (records of survey, corner records) and the BLM / state land office (original government plats and field notes).
3. The main types of descriptions
| Type | How it works | Short original example |
|---|---|---|
| Metes and bounds | Walks the perimeter. “Metes” are measurements (bearings and distances); “bounds” are the monuments and adjoining boundaries it touches. | “Beginning at an iron pin on the north line of Hollis Road; thence N 12°40′ E 310.00 feet…” |
| Rectangular survey (PLSS / aliquot) | Names a fraction of a section in a township and range. | “The W½ of the SE¼ of Section 9, T12S, R4E, Willamette Meridian.” |
| Lot and block (recorded plat) | Points to a lot on a recorded subdivision map. | “Lot 23, Block 5, Pine Hollow Subdivision, Plat Book 18, Page 61.” |
| Reference to adjoiners | Bounds the land by deeds already on record. | “Bounded on the north by land of Garza, on the east by Mill Creek, on the south by the county road and on the west by land of Petrie.” |
| Short form (“‘ly” parts) | Takes a measured slice of a known parcel. | “The south 100 feet of the east 200 feet of Lot 7.” |
| Strip / centerline | Describes a centerline and a width, for roads, pipelines and easements crossing many parcels. | “A strip of land 30 feet wide, lying 15 feet on each side of the following described centerline…” |
| Coordinate | Lists corner coordinates on a stated datum and projection. | “Beginning at a point with State Plane coordinates N 612,445.21, E 2,104,880.37 (NAD 83, Ohio South Zone, U.S. survey feet).” |
| Three-dimensional | Adds elevation limits for condos, air rights or subsurface. | “…lying above an elevation of 512.00 feet and below an elevation of 524.50 feet, NAVD 88.” |
Most real deeds combine types: a caption in lot-and-block or PLSS terms, then a metes-and-bounds body inside it.
4. Units, words and phrases
Distance and area units you will run into
| Unit | Equals | Notes |
|---|---|---|
| Gunter’s chain | 66 feet = 100 links = 4 rods | Standard unit of the PLSS. 80 chains = 1 mile. 10 square chains = 1 acre. |
| Link | 0.66 feet (7.92 inches) | 1/100 of a chain |
| Rod, pole or perch | 16.5 feet | Common in colonial metes and bounds. 320 rods = 1 mile. |
| Vara | About 33⅓ inches in Texas (2.7778 ft); about 33 inches in California (2.75 ft) | Length varied by place and time; check the local legal value. |
| League (Texas) | 5,000 varas square, about 4,428 acres | A “labor” is 1,000 varas square, about 177 acres. |
| Acre | 43,560 square feet | A 1-acre square is about 208.71 feet on a side. |
| Section | 1 mile square, nominally 640 acres | A quarter section is 160 acres; a quarter-quarter is 40 acres. |
| Township (PLSS) | 6 miles square, 36 sections, about 23,040 acres | |
| Rood | 1/4 acre | Shows up in old New England deeds (“12 acres, 2 roods, 14 rods”). |
| U.S. survey foot vs. international foot | Differ by 2 parts per million | Matters for state plane coordinates; the survey foot was retired for new work after 2022. |
Words that change the meaning
| Word or phrase | What it means when you read it |
|---|---|
| Point of Commencement (POC) vs. Point of Beginning (POB) | The POC is a known starting place used only to get to the parcel. The POB is the first corner of the parcel itself. Calls from the POC to the POB are “tie” calls and are not boundary lines. |
| Thence | “From there.” It separates one call from the next. |
| To / along / with / by | “To” a line stops at it. “Along” or “with” a line follows it, and when used for a whole multi-segment line it hides the individual segments, so avoid it in writing. Depending on the state, “to,” “by” or “along” a stream or road can carry title to its center. |
| Adjoining / adjacent / contiguous / coincident with | “Adjoining” means touching. “Adjacent” only means near. “Contiguous” has been read both ways. “Coincident with” leaves no doubt that two lines are the same line. |
| “Described in” vs. “conveyed in” | “The north line of land described in the deed to Smith” means the line as written. “The north line of land conveyed to Smith” means whatever Smith actually owns, which can differ (for example, it may run to the center of a street). |
| More or less | Tells you the stated distance or area is approximate and should give way to monuments and boundaries. |
| Parallel with / measured at right angles | “The north 50 feet” is measured perpendicular to the north line unless the description says otherwise (for example “measured along the east line”). |
| Prolongation / extension | Continues a line beyond its end on the same bearing (or the same curve). |
| Northerly, northeasterly, etc. | A general direction, not a precise bearing. Fine for naming a line (“the northerly line”), weak as a course to run. |
| Tangent / non-tangent | Whether the curve meets the previous line smoothly. “Non-tangent” means you need a radial bearing to place the curve. |
| NAP / “not a part” | An area on a plat that the subdivider did not include, such as a parcel owned by someone else. |
| Of record / per map / as shown on | Pulls in another recorded document as if its contents were written into this one. |
5. Bearings, azimuths and the basis of bearings
Quadrant bearings
A bearing starts from north or south and turns toward east or west, never more than 90°. N 35°15'20" E means: face north, turn 35 degrees, 15 minutes, 20 seconds toward east. 60 seconds = 1 minute, 60 minutes = 1 degree.
Reverse a bearing by swapping both letters: the reverse of N 35°15'20" E is S 35°15'20" W. A deed walking the other way around the parcel will show every bearing reversed.
Azimuths
An azimuth is measured clockwise from north, 0° to 360°. Conversions:
| Bearing | Azimuth |
|---|---|
| N θ E | θ |
| S θ E | 180° − θ |
| S θ W | 180° + θ |
| N θ W | 360° − θ |
Some older and some government work measured azimuths from south. Check the document’s convention before converting.
Basis of bearings
Bearings are only meaningful relative to a reference. Modern descriptions should say what that is: “Bearings are based on the east line of the NW¼ of Section 14 being N 0°12’33” W” or “Bearings are grid bearings of the Colorado State Plane Coordinate System, Central Zone, NAD 83.” Old deeds often used magnetic north, which wanders over time (declination), so a bearing from 1880 and one from 1990 along the same fence can differ by several degrees.
6. Reading the Public Land Survey System
The grid
- Each survey region starts from an initial point where a principal meridian (north-south) crosses a baseline (east-west). There are 37 principal meridians in the lower 48 states and Alaska.
- Townships are numbered north or south of the baseline (T3N, T7S). Ranges are numbered east or west of the meridian (R2E, R14W). Each township is about 6 miles square.
- Because meridians converge toward the pole, standard parallels (correction lines) every 24 miles reset the width. That is why roads jog at correction lines.
- Each township has 36 sections, numbered back and forth starting in the northeast corner:
Survey error and convergence are pushed into the north and west sides of a township. Sections along those edges (1–7, 18, 19, 30, 31) often have irregular government lots instead of clean quarter-quarters. Government lots also appear along lakes, rivers and grant boundaries.
Reading an aliquot description: read it backwards
Commas and semicolons matter. “The NE¼ and the N½ of the SE¼” is two tracts (240 acres). “The N½ of the NE¼ and SE¼” can be read as one tract or two. Writers should repeat each fraction in full.
Where the corners really are
In the PLSS, the corners set by the original government survey control, even if the section is not a perfect square. Quarter corners are found or rebuilt by government rules (in most states, the BLM’s Manual of Surveying Instructions). The center of a section is where lines between opposite quarter corners cross. “Halves” and “quarters” are measured between those found corners, not by assuming 2,640 feet.
7. Lots, blocks and recorded maps
A subdivision plat is a recorded map that splits a tract into numbered lots and blocks, dedicates streets, and shows dimensions, curves and monuments. Once recorded, “Lot 12, Block 4, Oak Terrace, per Plat Book 22, Page 15” carries the whole map into the deed by reference.
- Always cite the book and page (or instrument number) and the county. Two subdivisions can share a name.
- Read the plat’s notes: basis of bearings, monuments set, easements, setback lines, “NAP” areas and any later amended or vacated plats.
- When a lot is sold by number, the buyer usually takes title to the center of an adjoining public street (subject to the public’s easement) if the subdivider owned the street land, unless the deed or local law says otherwise.
- When the plat’s dimensions and the monuments set for the plat disagree, the original monuments generally control.
8. Reading metes and bounds step by step
- Find the frame. The caption limits the parcel to the SE¼ NW¼ of Section 30. Nothing outside that 40-acre square passes.
- Find the starting point. The center of section is the POC, a tie point. The first call is a tie, not a boundary.
- List every call as bearing + distance + what it runs to or along (the “bound”).
- Sketch it. West 250, north 180, east 250, south 180: a 250 × 180 ft four-sided parcel against the center line.
- Check closure. The bearings and distances should return to the POB. Here they close exactly.
- Check area. Roughly 250 × 180 = 45,000 sq ft ÷ 43,560 = 1.033 ac, which matches the stated area. (The exact figure is 44,997 sq ft, because the corners are 89°46′, not a perfect 90°.)
- Check the bounds. Two calls say “said center line.” That is a record boundary and outranks the measured distance if they ever disagree.
Closure: the math
For each line, latitude (north-south change) = distance × cos(azimuth) and departure (east-west change) = distance × sin(azimuth). Add all latitudes and all departures. In a perfect closed figure both sums are zero. The leftover distance is the error of closure, and dividing the total perimeter by it gives the precision ratio (e.g., 1:15,000). Modern boundary work usually closes better than 1:10,000. A big misclosure usually means a typo, a reversed bearing or a missing call.
Area comes from the coordinates by the “shoelace” (double meridian distance) method: area = ½ |Σ (xᵢ·yᵢ₊₁ − xᵢ₊₁·yᵢ)|.
9. “Northerly 50 feet” style descriptions
Short-form descriptions slice a known parcel with measured strips. They are clean when written carefully.
- “North 50 feet” is measured at right angles to the north line unless stated otherwise. If the lot’s side lines are not perpendicular, the strip is still bounded by a line parallel with the north line, 50 feet away.
- “North half” divides by area or by distance depending on local law and how the parcel was created. Spell it out: “the north half, by area” or “the northerly 66.00 feet.”
- When a street was widened and the lot lost land, “the south 30 feet of Lot 5” measures from the lot’s original line on the plat unless the deed says “the south 30 feet of the remainder.”
10. Curves
A curve in a description is an arc of a circle. Its parts:
| Element | Symbol | Formula (Δ in degrees) |
|---|---|---|
| Radius | R | Given |
| Central angle (delta) | Δ | Δ = L × 180 / (π R) |
| Arc length | L | L = π R Δ / 180 |
| Tangent length | T | T = R × tan(Δ/2) |
| Long chord | C | C = 2 R × sin(Δ/2) |
| External | E | E = R (1/cos(Δ/2) − 1) |
| Middle ordinate | M | M = R (1 − cos(Δ/2)) |
Any two of R, Δ, L, T or C define the curve. Good descriptions give three so a reader can catch errors.
- Non-tangent curves need a radial bearing: “…the beginning of a non-tangent curve, concave northerly, a radial line to said point bears N 14°02’31” W…” The center is 400 feet from the point along that radial.
- Compound curves turn the same way with different radii. Reverse curves turn the opposite way. Each joins at a common tangent point.
- Railroad and old highway curves were often defined by degree of curve (the central angle that subtends a 100-ft chord or arc): R ≈ 5,729.58 / D (arc definition). Convert before using modern formulas.
- If a curve’s stated length and delta disagree with its radius, check whether a digit was transposed, and compare against the plat and the adjoining calls before deciding which element is wrong.
11. What controls when the calls disagree
Descriptions often contain more information than needed, and the pieces do not always agree. Courts look for the intent of the parties, and over time they have settled on a general order of reliability. It is a guide, not a formula; a lower item can win when it clearly shows intent.
| Rank | Element | Why it ranks there |
|---|---|---|
| 1 | Rights of senior owners (an earlier deed from the same seller) | A seller cannot sell what he already sold. |
| 2 | Natural monuments (rivers, lakes, ridges, a named large tree) | Permanent and visible to the parties |
| 3 | Artificial monuments set for the parcel (iron pins, stone corners, marked lines) and original survey lines | The parties could see and rely on them |
| 4 | Adjoiners / record boundaries (“to the east line of land described to Rivas”) | Calls for an existing recorded line |
| 5 | Bearings (courses) | Measured, but measurement methods and bases change |
| 6 | Distances | Most error-prone of all measurements historically |
| 7 | Area / quantity (“containing 10 acres”) | Usually a computed result, so it ranks last unless the deed is clearly a sale of a quantity |
| — | Coordinates | Treated like measurements unless the document makes them controlling |
- A caption controls over the body where the body strays outside it.
- Specific beats general: “N 41°10′ E 300 feet to the iron pin” beats a later “thence northeasterly” in conflict.
- A call to a monument carries the distance to that monument, even if the stated distance is short or long, as long as the monument is the one intended and is undisturbed.
- A mistake obvious from the face of the deed (reversed bearing, transposed digits, “east” written for “west” when the parcel cannot close otherwise) may be corrected by reading the document as a whole.
- Where a deed is ambiguous, many courts resolve doubt against the person who wrote it (usually the grantor).
12. Water boundaries
- Riparian land touches a river or stream. Littoral land touches a lake or sea.
- On navigable waters, the state usually owns the bed up to the ordinary high water mark (inland) or the mean high tide line (coast), and private ownership stops there. On non-navigable streams, owners on each side usually own to the thread (center) unless the deed stops at the bank. State rules vary a lot.
- Meander lines in government surveys traced the shore to compute acreage. They are generally not the boundary; the water is.
- Accretion (gradual deposit of soil) and reliction (gradual retreat of water) add land to the shore owner. Erosion (gradual loss) takes it away. Avulsion (sudden change, like a flood cutting a new channel) does not move the boundary; it stays where the old channel was.
- When accreted land is divided among several shore owners, the usual approach gives each a share of the new shoreline in proportion to their share of the old one, with lines run from the old shore to the new.
- Describe water lines by the natural feature (“thence along the ordinary high water line of the Platte River”) rather than by bearings and distances alone, which freeze a line the law treats as moving.
13. Streets, easements and strips
Fee vs. easement
A road can be owned outright by the public (fee) or crossed only by a public right to use it (easement) while the abutting owners own the land underneath. The deed or dedication that created the road decides which. When a street easement is vacated (abandoned), the land usually reverts to the abutting owners, often to the center line, but a fee street that is vacated may stay with the public body or go elsewhere.
Easements
| Term | Meaning |
|---|---|
| Dominant estate | The land that benefits |
| Servient estate | The land that carries the burden |
| Appurtenant easement | Attached to a dominant parcel and passes with it on sale |
| Easement in gross | Belongs to a person or company (utilities, pipelines), not to a parcel |
| License | Permission that can usually be revoked; not an interest in land |
| Profit | A right to take something from the land (timber, minerals, gravel) |
| Overburdening | Using an easement more heavily or for different purposes than granted |
Writing and reading strip easements
The last sentence matters: without it the strip has square ends and leaves slivers or overlaps where it meets lot lines at an angle. Pipelines and highways also use stationing: “Station 12+50” means 1,250 feet along the centerline from Station 0+00.
14. Fences, occupation and title
Where people live and farm is not always where the paper says the line is. Several doctrines can move a boundary to match long occupation:
- Acquiescence: neighbors treat a line (often a fence) as the boundary for a long time, and the law treats it as the line.
- Agreed boundary: neighbors uncertain of the true line agree on one and occupy to it.
- Adverse possession: someone occupies land openly, continuously, exclusively and hostilely for the statutory period (and in some states pays the taxes), and gains title.
- Estoppel: one owner’s conduct leads another to rely on a line, and the first owner cannot later deny it.
These rights are usually unwritten until a court or a boundary-line agreement records them. A surveyor should show occupation that disagrees with the record line on the map; a description writer should describe the record line unless an agreement or judgment establishes another.
15. Common problems and how to resolve them
| Problem | What to do |
|---|---|
| Excess or shortage (the ground measures more or less than the plat) | In subdivisions, the excess or shortage is usually spread among the lots in proportion to their record dimensions (proportionate measurement). Where the last lot was a “remainder” by design, it may absorb the difference. Do not simply give all of it to the parcel you happen to be surveying. |
| Reversed bearing | If one call reversed makes the figure close and fits the adjoiners, the reversed reading is probably intended. |
| Transposed digits | 210.00 written for 201.00, or 45°31′ for 45°13′. Test the swap against closure and the plat. |
| Missing call | A gap in closure that matches one side of a known adjoining parcel often means a line was dropped. |
| Tie conflicts | If a parcel is tied to two monuments that do not agree, decide which the parties relied on, usually the closer, the older, or the one called for as a boundary rather than just a reference. |
| Indeterminate calls (“about,” “near,” “southerly”) | Lean on monuments and adjoiners; read general directions only as far as they go. |
| Unwritten assumptions | A call that turns “southerly” from an east-west line is often meant to be at right angles; a curve called “tangent” means no angle point. State these in writing rather than leaving them implied. |
| Gross vs. net area | Check whether the stated acreage includes the land under an adjoining road (gross) or excludes it (net). |
| Gaps and overlaps | Compare the description with each adjoining deed. Overlaps often go to the senior deed. |
16. Writing a description that holds up
Before writing
- Pull the vesting deed, the adjoining deeds, the recorded plat or government plat, and any record of survey.
- Know what is being conveyed and why (sale, split, easement, lease) and what must be excepted or reserved.
- Get a survey, or at least confirm the monuments and the basis of bearings.
The framework
- Caption: state, county, and the lot, section or recorded parcel the land lies in.
- Basis of bearings and datum if any bearings or coordinates follow.
- Commencement: a found, recoverable monument or recorded corner.
- Tie calls to the true point of beginning.
- Boundary calls in one direction around the parcel (most writers go clockwise), each with bearing, distance, curve data where needed, and what it runs to or along.
- Return to the true point of beginning.
- Area, “more or less.”
- Exceptions, reservations and appurtenances, each fully described.
Do
- Aim for short and unmistakable. Add words when they remove doubt.
- Call for monuments and adjoiners at each corner when they exist (“to an iron pipe set at the southeast corner of the land described in Instrument 2019-044512”).
- Use “described in” when you mean the paper line and “conveyed to” only when you intend the real ownership.
- Repeat full bearings, distances and fractions; avoid “same,” “aforesaid” chains a reader has to unwind.
- Check closure and area mathematically before recording.
- For strips, say how sidelines begin and end.
- When splitting one parcel into several, describe them so they share common lines exactly (“the northerly line of Parcel B is coincident with the southerly line of Parcel A”).
Don’t
- Don’t describe by fences, buildings or pavement unless you mean those things as the boundary.
- Don’t use street addresses, tax parcel numbers or “more or less” as the only identification.
- Don’t add “afterthought” calls that conflict with the main calls.
- Don’t use “along the easterly line” for a line made of many segments when one segment matters.
- Don’t leave the units, datum or basis of bearings to guesswork.
A clean template
Bearings are based on the east line of said SE¼ being N 0°09’44” W.
COMMENCING at the east quarter corner of said Section 11, a found brass cap;
thence S 0°09’44” E along the east line of said SE¼ a distance of 330.00 feet;
thence S 89°50’16” W 40.00 feet to the westerly right-of-way line of Ranch Road and the TRUE POINT OF BEGINNING;
thence continuing S 89°50’16” W 300.00 feet;
thence S 0°09’44” E 290.40 feet;
thence N 89°50’16” E 300.00 feet to said westerly right-of-way line;
thence N 0°09’44” W along said right-of-way line 290.40 feet to the TRUE POINT OF BEGINNING.
Containing 2.000 acres, more or less.”
17. Condos, air space and other 3-D parcels
- Condominium units are described by the recorded condominium plan or declaration (“Unit 4B as shown on the Condominium Plan recorded as Instrument…”), plus an undivided interest in the common elements.
- Air-space parcels add vertical limits: a horizontal outline plus upper and lower elevations on a named vertical datum (NAVD 88, NGVD 29 or a local datum).
- Subsurface parcels and mineral estates describe a depth range or a geologic formation; reservations often say “below a depth of 500 feet, without right of surface entry.”
- Avigation easements describe sloping planes above the ground around airports.
18. Tools for mapping and decoding
| Tool | Use it for |
|---|---|
| County recorder / register of deeds online search | Vesting deeds, adjoining deeds, plats, easements, records of survey |
| County GIS / assessor parcel viewer | A quick picture of where the parcel sits (approximate lines, not authoritative) |
| BLM General Land Office Records (glorecords.blm.gov) | Original federal patents, government survey plats and field notes for PLSS states |
| BLM PLSS GIS data and the “TRS” lookup tools | Turning township-range-section into a location on a map, and the reverse |
| State land office / Texas General Land Office | State patents, Texas abstracts and surveys |
| NGS coordinate tools (NCAT, datum transformations) | Converting between latitude/longitude, state plane, NAD 27 and NAD 83 |
| Deed plotting software (many free and paid options) and CAD/COGO programs | Plotting calls, checking closure and area, combining deeds |
| QGIS (free), Google Earth | Overlaying a plotted parcel on aerials and parcel layers |
| A legal dictionary (Black’s and similar) | Settling what a word legally means |
| A licensed land surveyor and a title company or attorney | Anything that will be relied on for a sale, loan, construction or dispute |
19. AI reference: a decoding procedure
This section is written so an AI assistant (or a person working methodically) can turn description text into structured data and check it.
Step-by-step procedure
- Normalize the text: fix OCR errors (° vs o, ‘ vs ′, ” vs ″, “l” vs “1”), expand abbreviations (N, S, E, W, Sec., Twp., Rng., Blk., P.O.B., T.P.O.B., R/W, C/L, ft., ch., lks.), and split into sentences at “thence.”
- Identify the jurisdiction: state, county, and system (PLSS, lot and block, metes and bounds, Texas survey and abstract, colonial).
- Extract the caption as the limiting parent parcel.
- Classify each part as caption, basis of bearings, commencement, tie call, boundary call, closing call, area statement, exception, reservation or appurtenance.
- Parse each call into: direction (bearing or azimuth), distance and unit, curve data, the monument or line it runs to or along, and qualifiers (“more or less,” “parallel with,” “at right angles”).
- Convert units to feet (chains × 66, rods × 16.5, links × 0.66, varas by local value).
- Compute coordinates from the POB; compute closure, precision and area.
- Cross-check: stated area vs. computed area; curve elements vs. each other; each “to the ___ line” against the referenced document; tie calls against found monuments.
- Flag issues by type (misclosure, reversed bearing candidate, transposed digits candidate, ambiguous word, missing basis of bearings, call outside caption, conflict between monument and distance) and rank them by the order of control in section 11.
- Report in plain language: what the parcel is, where it is, its size, its shape, what it touches, and what needs a surveyor’s attention.
A structured format for one parcel
{
"jurisdiction": {"state": "AZ", "county": "Yavapai"},
"system": "PLSS + metes and bounds",
"caption": "NE1/4 SE1/4 Sec 11, T8N, R2E, G&SRM",
"basis_of_bearings": {"line": "east line of SE1/4", "bearing": "N 0-09-44 W"},
"commencement": {"point": "east quarter corner Sec 11", "monument": "found brass cap"},
"ties": [
{"bearing": "S 0-09-44 E", "dist_ft": 330.00, "along": "east line of SE1/4"},
{"bearing": "S 89-50-16 W", "dist_ft": 40.00, "to": "W R/W line Ranch Road"}
],
"calls": [
{"bearing": "S 89-50-16 W", "dist_ft": 300.00},
{"bearing": "S 0-09-44 E", "dist_ft": 290.40},
{"bearing": "N 89-50-16 E", "dist_ft": 300.00, "to": "W R/W line Ranch Road"},
{"bearing": "N 0-09-44 W", "dist_ft": 290.40, "along": "W R/W line Ranch Road"}
],
"curve_example": {"type": "tangent", "concave": "SE", "radius_ft": 400.00,
"delta": "22-30-00", "arc_ft": 157.08},
"stated_area_ac": 2.000,
"exceptions": [], "reservations": [], "appurtenances": []
}
Patterns to recognize
| Text pattern | Parse as |
|---|---|
N 45°30'15" E 210.50 ft, N45-30-15E 210.5', North 45 degrees 30 minutes 15 seconds East | Quadrant bearing + distance |
Az 225°30'15" | Azimuth (confirm north or south origin) |
12.40 chains, 12 ch. 40 lks. | 12.40 × 66 = 818.40 ft |
40 poles / 40 rods / 40 perches | 660 ft |
R=400.00 Δ=22°30' L=157.08 | Curve; verify L = πRΔ/180 |
NE1/4 SW1/4 Sec 22 T5N R3W | Aliquot; read right to left; 40 ac nominal |
Lot 6, Blk 2, ___ Addition, PB 7 Pg 33 | Plat reference; fetch the plat |
Abstract 822, Survey No. 14 | Texas survey system |
to the TPOB, to the place of beginning | Closing call |
20. Free deed plotter
Paste one call per line. Use quadrant bearings and distances in feet, for example N 45 30 15 E 210.50, S45-30-15W 100 or N 0°14'10" W 180. Add ch, rods or links after a distance to convert. For a curve, enter its chord: chord N 30 00 00 E 156.07. The plotter draws the shape, reports closure, precision and area.
Working a land deal and stuck on a description? Bring it to a live call in our free community. We read real deeds, plot them and talk through what they mean.
This guide is general education, not legal or surveying advice. Rules vary by state; confirm anything you rely on with a licensed land surveyor and a real estate attorney or title company.